| Sl. No. |
Name of ROB |
Location Between Stations |
LC No. |
Physical Status |
| 1 |
Palghat–Sulthanpet (MOU) |
Palakkad Town station yard |
49 |
Work of Approach Portion of main bridge is completed. All works except super structure of span RP3-RP4 completed. Work of approach road of third arm in progress. |
| 2 |
Koratty Angady (MOU) |
Chalakkudy and Karukutty |
54 |
Approach Portion and the works up to substructure in the Railway portion completed. 2 adjacent spans on both sides of track span completed. Work of railway span is nearing completion. |
| 3 |
Parappanangady (MOU) |
Parappanangady and Vallikkunnu |
174A |
All spans completed. Road work is to be started and painting work in progress. |
| 4 |
Payyannore |
Payyannore - Cheruvathore |
261 |
All Works except one railway adjacent span completed. The Railway span is completed by railways. Stagging work of other adjacent span completed. |
| 5 |
Kainatty Road |
Badagara - Mukali |
216 |
All Works other than Railway adjacent span are completed .Work of railway portion is in progress. Adjacent span can be taken up only after the completion of the railway span by Railway. Work of adjacent spans is tendered by RBDCK. |
| 6 |
Mulamkunnathukav Yard. |
Mulamkunnathkavu& Poomkunnam. |
14 |
All Works other than Railway adjacent span are completed. Adjacent span can be taken up only after the completion of the railway span by Railway. Work of adjacent spans is tendered by RBDCK. |
| 7 |
Ponnurunni (MOU) |
Thripunithura and Ernakulam Junction |
2 |
All substructure works are completed. 17 slabs out of 18 are completed. started.CRS sanction awaited for the construction of railway span. |
| 8 |
Devdhar |
Tirur and Tanur |
172 |
All substructure works are completed. 18 slabs out of 18 are completed. The work of Railway portion is in progress which is doing by Southern Railways. |
| 9 |
Thirunavaya |
Thirunavaya yard |
170 |
All substructure works are completed. 19 slabs out of 21 are completed and the work is in progress. Adjacent span can be taken up only after the completion of Railway portion. Railways has started the work of railway portion. |
| 10 |
Anayara |
Kochuvel and Thiruvananthapuram |
578 |
All approach spans are completed. RE wall 100% completed. Road work on petta and Anayara side completed. Adjacent span at Petta side completed. Adjacent span at Anayara side started.
|
| 11 |
Cheruvathore (Padanna Road) |
Cheruvathore Yard |
268 |
All the slabs except adjacent spans are completed. Railway has started the work of railway span. |
| 12 |
Puliyanam |
Karukuty and Angamali |
59 |
All the works other than the adjacent spans are completed. Adjacent spans can be taken up only after the completion of the railway portion for which Railway is the executing agency. Railway pier cap completed. |
| 13 |
Koilandy |
Elathur and Quilandy |
201 |
The work is nearing completion. Inauguration is scheduled to be held on 20.4.2013 |
| 14 |
Kumaranalloor |
Kottayam and Ettumanoor |
33 |
20/33 pile completed. |
| 15 |
Mooledam |
Kottayam and Chingavanam |
|
11/13 pier completed |
| 16 |
Divine Nagar |
Chalakkudy - Karukutty |
52 |
Piling work completed. Pile cap-10/13, Pier-8/13,Pier cap-2/13 completed. |