At a Glance

I. List of 20 ROBs, which have been completed by RBDCK.

  Name of ROB LC No. Physical Status
1 IrumpanamYard (MOU) 8/15 Work completed and opened to traffic in June 2003.
2 Vellayil (MOU) 186 Work completed and opened to traffic in November 2003.
3 Vengali (MOU) 192 Work completed and opened to traffic in December 2003.
4 Tirur (MOU) 171 Work completed and opened to traffic in January 2004.
5 Meenchantha (MOU) 177 Work completed and opened to traffic in May 2004.
6 Thripoonithura (MOU) 8 Work completed and opened to traffic in July 2004.
7 Neeleswaram (MOU) 271 Work completed and opened to traffic in March 2005.
8 Chengottukavu (MOU) 199 Work completed and opened to traffic in August 2005.
9 S. Kalamassery (MOU) 67 Work completed and opened to traffic in October 2005.
10 Chalakkudy (MOU) 48 Work completed and opened to traffic in December 2005.
11 Vengalam (MOU) 196 Work completed and opened to traffic in 2006.
12 Kallettumkara (MOU) 43 Work completed and opened to traffic in April 2006.
13 Mundoor Rd. (MOU) 17 Work completed and opened to traffic in May 2006
14 Palghat Town- Victoria College. 50 Work completed and opened to traffic in January 2009
15 Muzhappilangad 232 Work completed and opened to traffic in June 2009
16 Nandi Bazar (MOU) 206 Work completed and opened to traffic in February 2010
17 Malampuzha Rd. 159 Work completed and opened to traffic in June 2010
18 Pulleppady-Thammanam 73 Work completed and opened to traffic in June 2010
19 Athani- Thrissur 13 Work completed and opened to traffic in September 2010
20 Bakel 276 Work Completed and opened to traffic in December 2010


II. Status of 16 ROB, where work is Ongoing

Sl. No. Name of ROB Location Between Stations LC No. Physical Status
1 Palghat–Sulthanpet (MOU) Palakkad Town station yard 49 Work of Approach Portion of main bridge is completed. All works except super structure of span RP3-RP4 completed. Work of approach road of third arm in progress.
2 Koratty Angady (MOU) Chalakkudy and Karukutty 54 Approach Portion and the works up to substructure in the Railway portion completed. 2 adjacent spans on both sides of track span completed. Work of railway span is nearing completion.
3 Parappanangady (MOU) Parappanangady and Vallikkunnu 174A All spans completed. Road work is to be started and painting work in progress.
4 Payyannore Payyannore - Cheruvathore 261 All Works except one railway adjacent span completed. The Railway span is completed by railways. Stagging work of other adjacent span completed.
5 Kainatty Road Badagara - Mukali 216 All Works other than Railway adjacent span are completed .Work of railway portion is in progress. Adjacent span can be taken up only after the completion of the railway span by Railway. Work of adjacent spans is tendered by RBDCK.
6 Mulamkunnathukav Yard. Mulamkunnathkavu& Poomkunnam. 14 All Works other than Railway adjacent span are completed. Adjacent span can be taken up only after the completion of the railway span by Railway. Work of adjacent spans is tendered by RBDCK.
7 Ponnurunni (MOU) Thripunithura and Ernakulam Junction 2 All substructure works are completed. 17 slabs out of 18 are completed. started.CRS sanction awaited for the construction of railway span.
8 Devdhar Tirur and Tanur 172 All substructure works are completed. 18 slabs out of 18 are completed. The work of Railway portion is in progress which is doing by Southern Railways.
9 Thirunavaya Thirunavaya yard 170 All substructure works are completed. 19 slabs out of 21 are completed and the work is in progress. Adjacent span can be taken up only after the completion of Railway portion. Railways has started the work of railway portion.
10 Anayara Kochuvel and Thiruvananthapuram 578 All approach spans are completed. RE wall 100% completed. Road work on petta and Anayara side completed. Adjacent span at Petta side completed. Adjacent span at Anayara side started.
11 Cheruvathore (Padanna Road) Cheruvathore Yard 268 All the slabs except adjacent spans are completed. Railway has started the work of railway span.
12 Puliyanam Karukuty and Angamali 59 All the works other than the adjacent spans are completed. Adjacent spans can be taken up only after the completion of the railway portion for which Railway is the executing agency. Railway pier cap completed.
13 Koilandy Elathur and Quilandy 201 The work is nearing completion. Inauguration is scheduled to be held on 20.4.2013
14 Kumaranalloor Kottayam and Ettumanoor 33 20/33 pile completed.
15 Mooledam Kottayam and Chingavanam 11/13 pier completed
16 Divine Nagar Chalakkudy - Karukutty 52 Piling work completed. Pile cap-10/13, Pier-8/13,Pier cap-2/13 completed.


Status of River Bridges

No. Name of Work Location Status
1 Edappallam – Morkkanad River Bridge Deposit Work for Palakkad District Panchayath All Sub structure works are completed and super structure works are in progress. 9 deck slabs out of 10are completed. Approach road work also in progress.
2 Station Kadavu River Bridge Ernakulam District Pile -27/79, Pilecaps - 2/12, Pier - 1/8 completed. Land acquisition for approach portion is in process.