Weekly Reports

Construction of River Bridge across Periyar Connecting Stationkadavu and Valiapazhampillithuruthu-Manager in Charge-Tinu Davis

Graph Project Graph

Weekly progress report as on 17-05-2013
 
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 Pile 79 27 52 52 0 0 52 0 0  
2 Pile Cap 12 4 8 8 0 0 8 0 0  
3 Pier 8 2 6 6 1 0 6 1 0  
4 Pier Cap 12 1 11 11 1 0 11 1 0  
5 Pedestals 12 1 11 11 1 0 11 1 0  
6 RE Wall 4 0 4 0 0 0 0 0 141  
7 Girder 11 0 11 7 0 0 7 0 82  
8 Deck Slab  11 0 11 6 0 0 3 0 76  
9 Hand rail Curb & Expansion Joints 11 0 11 0 0 0 0 0 107  
10 Drain spouts :               163  
11 Elasto -meric Paint :               206  
12                      
13                      
14                      
15                      
16                      
17                      
18                      
19                      
20                      
21                      
22                      
23                      
                       
Labour details                    
  date  manpower in nos                  
  11-05-13 1                  
  12-05-13 1                  
  13-05-13 1                  
  14-05-13 1                  
  15-05-13 1                  
  16-05-13 1                  
  17-05-13 1                  
 