ROB at Kainatty-Manager in charge-Muhammed Noufal
![]() |
Weekly progress report as on 14.06.2013 |
All the works of approach span except connecting spans to railway span are completed.Connecting spans can becompleted only after the completion of railway spans which is to be done by Southern Railways. The work has been tendered and NTP issued. |
|