Date of Tender notification
|
27.11.2010
|
|
Date of Agreement
|
17.01.2012
|
|
Notice to proceed with the work
|
21.05.2012
|
|
Expected date of completion
|
20.11.2013
|
|
Contract amount
|
16.84 Crores
|
|
Total Length of bridge
|
326 m
|
|
Length of Approach portion towards Paliyam
|
54.37 m
|
|
Length of Approach portion towards Thrissur
|
59.94 m
|
|
Slope of ROB towards Paliyam
|
1 in 19
|
|
Slope of ROB towards Thrissur
|
1 in 19
|
|
Width of Carriage way
|
7.5 m
|
|
Total width of bridge including foot path
|
10.5 m
|
|
Footpath |
Both side |
|
Period of completion
|
18 months
|
|
Estimated value of work |
Rs. 14.08 Crores |
|
Contractor for the project
|
Hope Constructions
|
|
Consultant
|
KITCO Ltd
|
|
Present status of the work
|
Pile -27/79, Pilecaps - 2/12, Pier - 1/8 completed
|