Construction of River Bridge across Periyar Connecting Stationkadavu and Valiapazhampillithuruthu-Manager in Charge-Tinu Davis
 
   

Date of Tender notification

27.11.2010

Date of Agreement

17.01.2012

Notice to proceed with the work

21.05.2012

Expected date of completion

20.11.2013

Contract amount

16.84 Crores

Total Length of bridge

326 m

Length of Approach portion towards Paliyam

54.37 m

Length of Approach portion towards Thrissur

59.94 m

Slope of ROB towards Paliyam

1 in 19

Slope of ROB towards Thrissur

1 in 19

Width of Carriage way

7.5 m

Total width of bridge including foot path

10.5 m

Footpath Both side

Period of completion

18 months

Estimated value of work Rs. 14.08 Crores

Contractor for the project

Hope Constructions

Consultant

KITCO Ltd

Present status of the work

Pile -27/79, Pilecaps - 2/12, Pier - 1/8 completed

 

 

 

 

 

 

 

 

 

 